Confidential Client

Project Details:

Owner: Confidential
General Contractor: Confidential
Duration of Work: 22 weeks
Subsurface Conditions: Ash ponds surrounded by clay berms, later replaced by compacted granular backfill
Approximate Key Quantities: 1,000 Controlled Modulus Columns (CMC)™ Rigid Inclusions

Project Overview:

This project involved the construction of two “scrubber” buildings and numerous auxiliary equipment units for a large coal-burning power station in Homer City, Pennsylvania. The two buildings house NID™ Flue Gas Desulfurization systems, which combine to eliminate the majority of pollution output from the plant. The two identical buildings each stand 120 feet tall with a footprint of 26,000 square feet, and rest on a foundation of alternating 4.5 foot thick mats and 12 inch slabs. The additional equipment structures included booster fans, mixing tanks, water silos, electrical enclosures and a compressor building. To improve the bearing capacity and keep total settlement requirements, Menard implemented a design-build ground improvement solution using Controlled Modulus Columns (CMC)™ Rigid Inclusions.

Ground Conditions:

The site selected for the two buildings and the auxiliary equipment pads included four ash ponds surrounded by clay berms. In the months leading up to CMC Rigid Inclusions installation, the ponds were dredged to depths of 20 feet from existing grade. The ash was replaced by 13 feet of compacted granular backfill bringing the site grade down about 7 feet. The berms consisted of medium stiff clay fill above weathered bedrock.

Specifications required reducing the total settlement of the building to less than ¾ of an inch. Before construction, ground improvement was specified to meet the settlement requirements and improve the bearing capacity of the soil.

Solution:

The Menard solution consisted of the design and installation of more than 1,000 CMC Rigid Inclusion elements to keep total settlement within project requirements. In the former pond areas, pre-drilling was employed to reach the bottom of the granular backfill. Then, Menard utilized a displacement method using a vibratory hammer to penetrate the compacted granular fill and medium stiff clay layer and reach termination at bedrock. In the areas outside the pond, a displacement auger was used to penetrate the clay fills. the combined displacement technique approach allowed the three-phase ground improvement work to be completed ahead of schedule and enabled the client to shorten the construction schedule.

Print this resource

Other Projects: