
ODOT I-75 Reconstruction and DiSalle Bridge Replacement
ODOT I-75 Reconstruction and DiSalle Bridge Replacement
Project Details:
Owner: Ohio Department of Transportation
General Contractor: Kokosing Construction Company
Date of Work: August 2019 - June 2022
Engineer: AECOM
Approximate Key Quantities: Wick Drains -10,833 EA and Controlled Modulus Columns (CMC)® - 2,915 EA
Description:
Ground Conditions:
Solution:
Wick drains, designed by the owner’s engineer, were recommended for embankments and walls where bearing capacity was not a concern. This was done to accelerate settlement created by the new fill placement and construction.
For the north and south bridge approaches along I-75, a more robust solution was required. The rationale was the stability calculations showed the proposed MSE walls could not be supported on the existing ground without excessive settlement. Initially, the recommended solution was large-diameter, grouted aggregate piers for the north approach, and deep soil-mix columns and panels for the south. Due to constructability and schedule concerns voiced during the bid phase, ODOT revised the specification to permit various forms of design-build, column-supported embankment solutions.
Menard elected to design -- and install -- CMC ground improvement elements for both the north and south approaches. The robust grid-array of CMCs, some reinforced and often in conjunction with geogrids, met the performance requirements for the walls. To assist in the installation and ultimately improve efficiency and schedule a significant pre-drilling program was employed on the north and south approaches. Menard performed upwards of 10 load tests, and the fill was monitored for settlement and pore pressure to ensure the stability of the wall.
Coordinating closely with Kokosing, which provided earthwork and monitoring assistance, Menard successfully designed and installed an effective ground improvement system for the ODOT I-75 Reconstruction and DiSalle Bridge Replacement project in Ohio.
Print this resource