Project Details:
Owner:City of Norfolk, Department of Utilities
General Contractor: ASI Constructors, Inc.
Duration of Work: 4 weeks
Subsurface Conditions: Sand fill
Approximate Key Quantities: Vibrocompaction - 254 Points
Project Overview:
Ground Conditions:
Solution:
Vibrocompaction is a ground improvement technique that involves penetration of loose foundation soils utilizing an electrically powered Vibro probe. The soil densification that occurs, improves bearing capacity and reduces potential for liquefaction and excessive settlements.
US Wick Drain’s innovative proposal of Vibrocompaction was a good fit for this project because it eliminated the need for dewatering. The probe was able to penetrate the placed fill down to the depth of the existing downstream mudline without the removal of water.
There were a total of 254 compaction points advanced to maximum depths of 16 feet.
Other Projects:
- Western Branch Dam Downstream Bermamanda2022-11-28T04:00:23+01:00
Western Branch Dam Downstream Berm
- Charleston Harbor Resort Expansionamanda2022-11-22T04:49:32+01:00
Charleston Harbor Resort Expansion
- Goya Foods Warehouse & Headquartersamanda2022-11-22T04:51:27+01:00
Goya Foods Warehouse & Headquarters
- Garden State Parkway Bridge Over Mullica Riveramanda2022-11-22T04:51:48+01:00
Garden State Parkway Bridge Over Mullica River
- Grand Valley State University – L. William Seidman Centeramanda2022-11-22T04:52:02+01:00
Grand Valley State University – L. William Seidman Center
- Interstate 78 & Garden State Parkwayamanda2022-11-22T04:53:18+01:00
Interstate 78 & Garden State Parkway
- Port of Gulfport Restoration Programamanda2022-11-22T04:55:06+01:00
Port of Gulfport Restoration Program
- Greenside Aircraft Taxiway and Hangar Complexamanda2022-11-22T04:55:33+01:00
Greenside Aircraft Taxiway and Hangar Complex
- Confidential Client Office Buildingamanda2022-11-22T04:56:03+01:00
Confidential Client Office Building
- Unilever Ice Cream Freezer Warehouseamanda2022-11-22T04:57:20+01:00
Unilever Ice Cream Freezer Warehouse
- Allegheny Health Network McCandlessamanda2022-11-22T04:59:48+01:00
Allegheny Health Network McCandless
- O’Fallon Wastewater Treatment Plantamanda2022-11-22T23:01:51+01:00
O’Fallon Wastewater Treatment Plant
- AdventHealth Tower & Central Energy Plantamanda2022-11-22T05:03:16+01:00
AdventHealth Tower & Central Energy Plant
- Confidential Client – Raceland, LAamanda2022-11-23T02:27:59+01:00
Confidential Client – Raceland, LA
- Port of Charleston HLT Wall Remediationamanda2022-11-23T02:29:46+01:00
Port of Charleston HLT Wall Remediation
- Jeannette Elliott Manufacturing Facilityamanda2022-11-23T02:33:40+01:00
Jeannette Elliott Manufacturing Facility
- NASA John H. Glenn Research Centeramanda2022-11-23T02:49:17+01:00
NASA John H. Glenn Research Center