Hancock International Airport - Deicing Storage Tanks
Hancock International Airport - Deicing Storage Tanks
Project Details:
Owner: Syracuse Regional Airport Authority
General Contractor: The Wesson Group, LLC
Date of Work: March 2019 - April 2019
Engineer: CME Associates, Inc.
Approximate Key Quantities: Controlled Modulus Columns (CMC)® - 434 EA.
Description:
Ground Conditions:
Solution:
Deep foundations were originally considered for ground improvement. However, Menard provided an economical and time-saving solution with CMCs. Menard’s solution included 434 CMCs installed to a maximum depth of 46 ft. The slab loads were designed with an allowable bearing floor pressure of 3,200 psf. The design
provided for approximately 3 in of post-construction settlement, meeting the performance criteria of the new deicing storage tanks.
Due to the scope of this project, the design required approval from both the tank builder and the geotechnical engineer of record, with whom Menard worked closely throughout the project. Menard overcame Syracuse’s harsh winter conditions and successfully installed 434 CMCs to support two new deicing tanks.